Tariff Breakdown
Description
Distance
Voltage
Capacity
All Seasons (ZAR)
High Season (ZAR)
Low Season (ZAR)
Consumption - off-peak
<=300km
<500V
Not specified
0.2140/kWh
Consumption - off-peak
>300km<=600km
<500V
Not specified
0.2160/kWh
Consumption - off-peak
>600km<=900km
<500V
Not specified
0.2176/kWh
Consumption - off-peak
>900km
<500V
Not specified
0.2199/kWh
Consumption - off-peak
<=300km
>=500V<66kV
Not specified
0.2074/kWh
Consumption - off-peak
>300km<=600km
>=500V<66kV
Not specified
0.2093/kWh
Consumption - off-peak
>600km<=900km
>=500V<66kV
Not specified
0.2113/kWh
Consumption - off-peak
>900km
>=500V<66kV
Not specified
0.2132/kWh
Consumption - off-peak
<=300km
>=66kV<132kV
Not specified
0.2004/kWh
Consumption - off-peak
>300km<=600km
>=66kV<132kV
Not specified
0.2024/kWh
Consumption - off-peak
>600km<=900km
>=66kV<132kV
Not specified
0.2039/kWh
Consumption - off-peak
>900km
>=66kV<132kV
Not specified
0.2060/kWh
Consumption - off-peak
<=300km
>132kV
Not specified
0.1940/kWh
Consumption - off-peak
>300km<=600km
>132kV
Not specified
0.1957/kWh
Consumption - off-peak
>600km<=900km
>132kV
Not specified
0.1973/kWh
Consumption - off-peak
>900km
>132kV
Not specified
0.1992/kWh
Consumption - peak
<=300km
<500V
Not specified
1.6109/kWh
Consumption - peak
>300km<=600km
<500V
Not specified
1.6262/kWh
Consumption - peak
>600km<=900km
<500V
Not specified
1.6413/kWh
Consumption - peak
>900km
<500V
Not specified
1.6570/kWh
Consumption - peak
<=300km
>=500V<66kV
Not specified
1.5561/kWh
Consumption - peak
>300km<=600km
>=500V<66kV
Not specified
1.5708/kWh
Consumption - peak
>600km<=900km
>=500V<66kV
Not specified
1.5866/kWh
Consumption - peak
>900km
>=500V<66kV
Not specified
1.6007/kWh
Consumption - standard
<=300km
<500V
Not specified
0.4686/kWh
Consumption - standard
>300km<=600km
<500V
Not specified
0.4724/kWh
Consumption - standard
>600km<=900km
<500V
Not specified
0.4762/kWh
Consumption - standard
>900km
<500V
Not specified
0.4802/kWh
Consumption - standard
<=300km
>=500V<66kV
Not specified
0.4505/kWh
Consumption - standard
>300km<=600km
>=500V<66kV
Not specified
0.4541/kWh
Consumption - standard
>600km<=900km
>=500V<66kV
Not specified
0.4580/kWh
Consumption - standard
>900km
>=500V<66kV
Not specified
0.4617/kWh
Consumption - standard
<=300km
>=66kV<132kV
Not specified
0.4349/kWh
Consumption - standard
>300km<=600km
>=66kV<132kV
Not specified
0.4384/kWh
Consumption - standard
>600km<=900km
>=66kV<132kV
Not specified
0.4419/kWh
Consumption - standard
>900km
>=66kV<132kV
Not specified
0.4457/kWh
Consumption - standard
<=300km
>132kV
Not specified
0.4162/kWh
Consumption - standard
>300km<=600km
>132kV
Not specified
0.4197/kWh
Consumption - standard
>600km<=900km
>132kV
Not specified
0.4230/kWh
Consumption - standard
>900km
>132kV
Not specified
0.4268/kWh
Daily administration charge
Not specified
Not specified
<=100kVA
1.3800/d
Daily administration charge
Not specified
Not specified
>100kVA<=500kVA
7.9900/d
Daily administration charge
Not specified
Not specified
>1MVA
39.5300/d
Daily administration charge
Not specified
Not specified
>1MVA Key cust
54.9000/d
Daily administration charge
Not specified
Not specified
>500kVA<=1MVA
15.9100/d
Daily service charge
Not specified
Not specified
<=100kVA
6.2600/d
Daily service charge
Not specified
Not specified
>100kVA<=500kVA
28.5100/d
Daily service charge
Not specified
Not specified
>1MVA
87.7300/d
Daily service charge
Not specified
Not specified
>1MVA Key cust
1719.2600/d
Daily service charge
Not specified
Not specified
>500kVA<=1MVA
87.7300/d
Electrification and rural subsidy
Not specified
Not specified
Not specified
0.0324/kWh
Environmental levy
Not specified
Not specified
Not specified
0.0200/kWh
Network access charge
<=300km
<500V
Not specified
11.5200/kVA
Network access charge
>300km<=600km
<500V
Not specified
11.5600/kVA
Network access charge
>600km<=900km
<500V
Not specified
11.6000/kVA
Network access charge
>900km
<500V
Not specified
11.6200/kVA
Network access charge
<=300km
>=500V<66kV
Not specified
10.5500/kVA
Network access charge
>300km<=600km
>=500V<66kV
Not specified
10.5800/kVA
Network access charge
>600km<=900km
>=500V<66kV
Not specified
10.6200/kVA
Network access charge
>900km
>=500V<66kV
Not specified
10.6600/kVA
Network access charge
>300km<=600km
>=66kV<132kV
Not specified
10.2600/kVA
Network access charge
>600km<=900km
>=66kV<132kV
Not specified
10.3000/kVA
Network access charge
>900km
>=66kV<132kV
Not specified
10.3100/kVA
Network access charge
>300km<=600km
>132kV
Not specified
4.3700/kVA
Network access charge
>600km<=900km
>132kV
Not specified
4.4300/kVA
Network access charge
>900km
>132kV
Not specified
4.4600/kVA
Reactive energy charge
Not specified
Not specified
Not specified
0.0269/kVARh
Historical Cost Trends
Transform Your Energy Management
Unlock the Power of Real-Time Insights
With Augos
By choosing Augos, you’re not just buying hardware - you’re investing in an intelligent, integrated ecosystem designed to maximise your operational performance and sustainability.