Open data for 2016/17 — every charge with its unit, season and bands:

Free to reuse under CC BY 4.0. Please credit “Augos Tariff Database” with a link to this page.

Tariff Breakdown

Description
Distance
Voltage
Capacity
All Seasons (ZAR)
High Season (ZAR)
Low Season (ZAR)
Affordability subsidy charge
Not specified
Not specified
Not specified
0.0265/kWh
Ancillary service charge
Not specified
<500V
Not specified
0.0036/kWh
Ancillary service charge
Not specified
>=500V<66kV
Not specified
0.0035/kWh
Ancillary service charge
Not specified
>=66kV<132kV
Not specified
0.0033/kWh
Ancillary service charge
Not specified
>132kV
Not specified
0.0031/kWh
Consumption - standard
<=300km
<500V
Not specified
0.6726/kWh
0.5229/kWh
Consumption - standard
>300km<=600km
<500V
Not specified
0.6817/kWh
0.5286/kWh
Consumption - standard
>600km<=900km
<500V
Not specified
0.6880/kWh
0.5338/kWh
Consumption - standard
>900km
<500V
Not specified
0.6953/kWh
0.5392/kWh
Consumption - standard
<=300km
>=500V<66kV
Not specified
0.6370/kWh
0.4972/kWh
Consumption - standard
>300km<=600km
>=500V<66kV
Not specified
0.6503/kWh
0.5073/kWh
Consumption - standard
>600km<=900km
>=500V<66kV
Not specified
0.6568/kWh
0.5125/kWh
Consumption - standard
>900km
>=500V<66kV
Not specified
0.6632/kWh
0.5175/kWh
Consumption - standard
<=300km
>=66kV<132kV
Not specified
0.6323/kWh
0.4912/kWh
Consumption - standard
>300km<=600km
>=66kV<132kV
Not specified
0.6455/kWh
0.5012/kWh
Consumption - standard
>600km<=900km
>=66kV<132kV
Not specified
0.6519/kWh
0.5062/kWh
Consumption - standard
>900km
>=66kV<132kV
Not specified
0.6586/kWh
0.5112/kWh
Consumption - standard
<=300km
>132kV
Not specified
0.5915/kWh
0.4599/kWh
Consumption - standard
>300km<=600km
>132kV
Not specified
0.6039/kWh
0.4693/kWh
Consumption - standard
>600km<=900km
>132kV
Not specified
0.6098/kWh
0.4741/kWh
Consumption - standard
>900km
>132kV
Not specified
0.6163/kWh
0.4793/kWh
Daily administration charge
Not specified
Not specified
>1MVA
80.1100/d
Daily administration charge
Not specified
Not specified
>1MVA Key cust
111.2400/d
Daily service charge
Not specified
Not specified
>1MVA
177.7500/d
Daily service charge
Not specified
Not specified
>1MVA Key cust
3483.1600/d
Demand charge
<=300km
<500V
Not specified
204.6700/kVA
28.6000/kVA
Demand charge
>300km<=600km
<500V
Not specified
206.7800/kVA
28.8800/kVA
Demand charge
>600km<=900km
<500V
Not specified
208.8900/kVA
29.1800/kVA
Demand charge
>900km
<500V
Not specified
210.9200/kVA
29.4600/kVA
Demand charge
<=300km
>=500V<66kV
Not specified
198.0900/kVA
27.6900/kVA
Demand charge
>300km<=600km
>=500V<66kV
Not specified
200.1000/kVA
27.9400/kVA
Demand charge
>600km<=900km
>=500V<66kV
Not specified
202.1100/kVA
28.2500/kVA
Demand charge
>900km
>=500V<66kV
Not specified
204.1400/kVA
28.4900/kVA
Demand charge
<=300km
>=66kV<132kV
Not specified
190.8800/kVA
26.6800/kVA
Demand charge
>300km<=600km
>=66kV<132kV
Not specified
192.7700/kVA
26.9300/kVA
Demand charge
>600km<=900km
>=66kV<132kV
Not specified
194.7100/kVA
27.2000/kVA
Demand charge
>900km
>=66kV<132kV
Not specified
196.7000/kVA
27.4800/kVA
Demand charge
<=300km
>132kV
Not specified
184.1300/kVA
25.7300/kVA
Demand charge
>300km<=600km
>132kV
Not specified
186.0100/kVA
25.9700/kVA
Demand charge
>600km<=900km
>132kV
Not specified
187.8700/kVA
26.2300/kVA
Demand charge
>900km
>132kV
Not specified
189.7700/kVA
26.5000/kVA
Electrification and rural subsidy
Not specified
Not specified
Not specified
0.0693/kWh
Excess NAC charge
<=300km
<500V
Not specified
7.7900/kVA
Excess NAC charge
>300km<=600km
<500V
Not specified
7.8500/kVA
Excess NAC charge
>600km<=900km
<500V
Not specified
7.9500/kVA
Excess NAC charge
>900km
<500V
Not specified
7.9800/kVA
Excess NAC charge
<=300km
>=500V<66kV
Not specified
7.1200/kVA
Excess NAC charge
>300km<=600km
>=500V<66kV
Not specified
7.1900/kVA
Excess NAC charge
>600km<=900km
>=500V<66kV
Not specified
7.2500/kVA
Excess NAC charge
>900km
>=500V<66kV
Not specified
7.3400/kVA
Excess NAC charge
<=300km
>=66kV<132kV
Not specified
6.9400/kVA
Excess NAC charge
>300km<=600km
>=66kV<132kV
Not specified
6.9900/kVA
Excess NAC charge
>600km<=900km
>=66kV<132kV
Not specified
7.0300/kVA
Excess NAC charge
>900km
>=66kV<132kV
Not specified
7.0900/kVA
Excess NAC charge
<=300km
>132kV
Not specified
8.7600/kVA
Excess NAC charge
>300km<=600km
>132kV
Not specified
8.8500/kVA
Excess NAC charge
>600km<=900km
>132kV
Not specified
8.9700/kVA
Excess NAC charge
>900km
>132kV
Not specified
21.5400/kVA
Network access charge
Not specified
<500V
Not specified
15.4800/kVA
Network access charge
Not specified
>=500V<66kV
Not specified
14.2000/kVA
Network access charge
Not specified
>=66kV<132kV
Not specified
5.0700/kVA
Network demand charge
Not specified
<500V
Not specified
29.3500/kVA
Network demand charge
Not specified
>=500V<66kV
Not specified
26.9300/kVA
Network demand charge
Not specified
>=66kV<132kV
Not specified
9.3900/kVA
Transmission network charge
<=300km
<500V
Not specified
7.7900/kVA
Transmission network charge
>300km<=600km
<500V
Not specified
7.8500/kVA
Transmission network charge
>600km<=900km
<500V
Not specified
7.9500/kVA
Transmission network charge
>900km
<500V
Not specified
7.9800/kVA
Transmission network charge
<=300km
>=500V<66kV
Not specified
7.1200/kVA
Transmission network charge
>300km<=600km
>=500V<66kV
Not specified
7.1900/kVA
Transmission network charge
>600km<=900km
>=500V<66kV
Not specified
7.2500/kVA
Transmission network charge
>900km
>=500V<66kV
Not specified
7.3400/kVA
Transmission network charge
<=300km
>=66kV<132kV
Not specified
6.9400/kVA
Transmission network charge
>300km<=600km
>=66kV<132kV
Not specified
6.9900/kVA
Transmission network charge
>600km<=900km
>=66kV<132kV
Not specified
7.0300/kVA
Transmission network charge
>900km
>=66kV<132kV
Not specified
7.0900/kVA
Transmission network charge
<=300km
>132kV
Not specified
8.7600/kVA
Transmission network charge
>300km<=600km
>132kV
Not specified
8.8500/kVA
Transmission network charge
>600km<=900km
>132kV
Not specified
8.9700/kVA
Transmission network charge
>900km
>132kV
Not specified
9.0400/kVA
Urban low voltage subsidy charge
Not specified
>=66kV<132kV
Not specified
12.5000/kVA
Urban low voltage subsidy charge
Not specified
>132kV
Not specified
12.5000/kVA

Historical Cost Trends