Tariff Breakdown

Description
Distance
Voltage
Capacity
All Seasons (ZAR)
High Season (ZAR)
Low Season (ZAR)
Ancillary service charge
Not specified
<500V
Not specified
0.0036/kWh
Ancillary service charge
Not specified
>=500V<66kV
Not specified
0.0035/kWh
Ancillary service charge
Not specified
>=66kV<132kV
Not specified
0.0033/kWh
Ancillary service charge
Not specified
>132kV
Not specified
0.0031/kWh
Consumption - standard
<=300km
<500V
Not specified
0.6908/kWh
0.5372/kWh
Consumption - standard
>300km<=600km
<500V
Not specified
0.6999/kWh
0.5430/kWh
Consumption - standard
>600km<=900km
<500V
Not specified
0.7066/kWh
0.5482/kWh
Consumption - standard
>900km
<500V
Not specified
0.7141/kWh
0.5537/kWh
Consumption - standard
<=300km
>=500V<66kV
Not specified
0.6542/kWh
0.5106/kWh
Consumption - standard
>300km<=600km
>=500V<66kV
Not specified
0.6678/kWh
0.5209/kWh
Consumption - standard
>600km<=900km
>=500V<66kV
Not specified
0.6745/kWh
0.5263/kWh
Consumption - standard
>900km
>=500V<66kV
Not specified
0.6812/kWh
0.5314/kWh
Consumption - standard
<=300km
>=66kV<132kV
Not specified
0.6494/kWh
0.5043/kWh
Consumption - standard
>300km<=600km
>=66kV<132kV
Not specified
0.6629/kWh
0.5148/kWh
Consumption - standard
>600km<=900km
>=66kV<132kV
Not specified
0.6695/kWh
0.5200/kWh
Consumption - standard
>900km
>=66kV<132kV
Not specified
0.6762/kWh
0.5250/kWh
Consumption - standard
<=300km
>132kV
Not specified
0.6075/kWh
0.4724/kWh
Consumption - standard
>300km<=600km
>132kV
Not specified
0.6200/kWh
0.4820/kWh
Consumption - standard
>600km<=900km
>132kV
Not specified
0.6263/kWh
0.4869/kWh
Consumption - standard
>900km
>132kV
Not specified
0.6331/kWh
0.4923/kWh
Daily administration charge
Not specified
Not specified
>1MVA
80.0000/d
Daily administration charge
Not specified
Not specified
>1MVA Key cust
111.0700/d
Daily service charge
Not specified
Not specified
>1MVA
177.4800/d
Daily service charge
Not specified
Not specified
>1MVA Key cust
3477.9300/d
Demand charge
<=300km
<500V
Not specified
206.2600/kVA
28.8200/kVA
Demand charge
>300km<=600km
<500V
Not specified
208.4000/kVA
29.1000/kVA
Demand charge
>600km<=900km
<500V
Not specified
210.5100/kVA
29.4100/kVA
Demand charge
>900km
<500V
Not specified
212.5800/kVA
29.7000/kVA
Demand charge
<=300km
>=500V<66kV
Not specified
199.6400/kVA
27.9200/kVA
Demand charge
>300km<=600km
>=500V<66kV
Not specified
201.6500/kVA
28.1600/kVA
Demand charge
>600km<=900km
>=500V<66kV
Not specified
203.7000/kVA
28.4700/kVA
Demand charge
>900km
>=500V<66kV
Not specified
205.7300/kVA
28.7200/kVA
Demand charge
<=300km
>=66kV<132kV
Not specified
192.3700/kVA
26.8800/kVA
Demand charge
>300km<=600km
>=66kV<132kV
Not specified
194.2800/kVA
27.1500/kVA
Demand charge
>600km<=900km
>=66kV<132kV
Not specified
196.2400/kVA
27.4000/kVA
Demand charge
>900km
>=66kV<132kV
Not specified
198.2200/kVA
27.7000/kVA
Demand charge
<=300km
>132kV
Not specified
185.5700/kVA
25.9200/kVA
Demand charge
>300km<=600km
>132kV
Not specified
187.4600/kVA
26.1800/kVA
Demand charge
>600km<=900km
>132kV
Not specified
189.3500/kVA
26.4500/kVA
Demand charge
>900km
>132kV
Not specified
191.2500/kVA
26.7000/kVA
Electrification and rural subsidy
Not specified
Not specified
Not specified
0.0691/kWh
Excess NAC charge
<=300km
<500V
Not specified
7.7900/kVA
Excess NAC charge
>300km<=600km
<500V
Not specified
7.8300/kVA
Excess NAC charge
>600km<=900km
<500V
Not specified
7.9300/kVA
Excess NAC charge
>900km
<500V
Not specified
7.9700/kVA
Excess NAC charge
<=300km
>=500V<66kV
Not specified
7.1100/kVA
Excess NAC charge
>300km<=600km
>=500V<66kV
Not specified
7.1800/kVA
Excess NAC charge
>600km<=900km
>=500V<66kV
Not specified
7.2400/kVA
Excess NAC charge
>900km
>=500V<66kV
Not specified
7.3100/kVA
Excess NAC charge
<=300km
>=66kV<132kV
Not specified
6.9200/kVA
Excess NAC charge
>300km<=600km
>=66kV<132kV
Not specified
6.9700/kVA
Excess NAC charge
>600km<=900km
>=66kV<132kV
Not specified
7.0300/kVA
Excess NAC charge
>900km
>=66kV<132kV
Not specified
7.0800/kVA
Excess NAC charge
<=300km
>132kV
Not specified
8.7600/kVA
Excess NAC charge
>300km<=600km
>132kV
Not specified
8.8400/kVA
Excess NAC charge
>600km<=900km
>132kV
Not specified
8.8600/kVA
Excess NAC charge
>900km
>132kV
Not specified
9.0300/kVA
Network access charge
<=300km
<500V
Not specified
15.5400/kVA
Network access charge
>300km<=600km
<500V
Not specified
15.5400/kVA
Network access charge
>600km<=900km
<500V
Not specified
15.5400/kVA
Network access charge
>900km
<500V
Not specified
15.5400/kVA
Network access charge
<=300km
>=500V<66kV
Not specified
14.2500/kVA
Network access charge
>300km<=600km
>=500V<66kV
Not specified
14.2500/kVA
Network access charge
>600km<=900km
>=500V<66kV
Not specified
14.2500/kVA
Network access charge
>900km
>=500V<66kV
Not specified
14.2500/kVA
Network access charge
<=300km
>=66kV<132kV
Not specified
5.1000/kVA
Network access charge
>300km<=600km
>=66kV<132kV
Not specified
5.1000/kVA
Network access charge
>600km<=900km
>=66kV<132kV
Not specified
5.1000/kVA
Network access charge
>900km
>=66kV<132kV
Not specified
5.1000/kVA
Transmission network charge
<=300km
<500V
Not specified
7.7900/kVA
Transmission network charge
>300km<=600km
<500V
Not specified
7.8300/kVA
Transmission network charge
>600km<=900km
<500V
Not specified
7.9300/kVA
Transmission network charge
>900km
<500V
Not specified
7.9700/kVA
Transmission network charge
<=300km
>=500V<66kV
Not specified
7.1100/kVA
Transmission network charge
>300km<=600km
>=500V<66kV
Not specified
7.1800/kVA
Transmission network charge
>600km<=900km
>=500V<66kV
Not specified
7.2400/kVA
Transmission network charge
>900km
>=500V<66kV
Not specified
7.3100/kVA
Transmission network charge
<=300km
>=66kV<132kV
Not specified
6.9200/kVA
Transmission network charge
>300km<=600km
>=66kV<132kV
Not specified
6.9700/kVA
Transmission network charge
>600km<=900km
>=66kV<132kV
Not specified
7.0300/kVA
Transmission network charge
>900km
>=66kV<132kV
Not specified
7.0800/kVA
Transmission network charge
<=300km
>132kV
Not specified
8.7600/kVA
Transmission network charge
>300km<=600km
>132kV
Not specified
8.8400/kVA
Transmission network charge
>600km<=900km
>132kV
Not specified
8.9600/kVA
Transmission network charge
>900km
>132kV
Not specified
9.0300/kVA
Urban low voltage subsidy charge
Not specified
>=66kV<132kV
Not specified
12.4800/kVA
Urban low voltage subsidy charge
Not specified
>132kV
Not specified
12.4800/kVA