Open data for 2019/20 — every charge with its unit, season and bands:

Free to reuse under CC BY 4.0. Please credit “Augos Tariff Database” with a link to this page.

Tariff Breakdown

Description
Distance
Voltage
Capacity
All Seasons (ZAR)
High Season (ZAR)
Low Season (ZAR)
Ancillary service charge
Not specified
<500V
Not specified
0.0045/kWh
Ancillary service charge
Not specified
>=500V<66kV
Not specified
0.0044/kWh
Ancillary service charge
Not specified
>=66kV<132kV
Not specified
0.0040/kWh
Ancillary service charge
Not specified
>132kV
Not specified
0.0038/kWh
Consumption - standard
<=300km
<500V
Not specified
0.8573/kWh
0.6666/kWh
Consumption - standard
>300km<=600km
<500V
Not specified
0.8685/kWh
0.6738/kWh
Consumption - standard
>600km<=900km
<500V
Not specified
0.8768/kWh
0.6802/kWh
Consumption - standard
>900km
<500V
Not specified
0.8862/kWh
0.6871/kWh
Consumption - standard
<=300km
>=500V<66kV
Not specified
0.8118/kWh
0.6337/kWh
Consumption - standard
>300km<=600km
>=500V<66kV
Not specified
0.8287/kWh
0.6464/kWh
Consumption - standard
>600km<=900km
>=500V<66kV
Not specified
0.8370/kWh
0.6531/kWh
Consumption - standard
>900km
>=500V<66kV
Not specified
0.8454/kWh
0.6594/kWh
Consumption - standard
<=300km
>=66kV<132kV
Not specified
0.8058/kWh
0.6258/kWh
Consumption - standard
>300km<=600km
>=66kV<132kV
Not specified
0.8226/kWh
0.6389/kWh
Consumption - standard
>600km<=900km
>=66kV<132kV
Not specified
0.8308/kWh
0.6453/kWh
Consumption - standard
>900km
>=66kV<132kV
Not specified
0.8391/kWh
0.6515/kWh
Consumption - standard
<=300km
>132kV
Not specified
0.7539/kWh
0.5862/kWh
Consumption - standard
>300km<=600km
>132kV
Not specified
0.7694/kWh
0.5982/kWh
Consumption - standard
>600km<=900km
>132kV
Not specified
0.7771/kWh
0.6042/kWh
Consumption - standard
>900km
>132kV
Not specified
0.7856/kWh
0.6109/kWh
Daily administration charge
Not specified
Not specified
>1MVA
99.2800/d
Daily administration charge
Not specified
Not specified
>1MVA Key cust
137.8300/d
Daily service charge
Not specified
Not specified
>1MVA
220.2400/d
Daily service charge
Not specified
Not specified
>1MVA Key cust
4315.8900/d
Demand charge
<=300km
<500V
Not specified
255.9600/kVA
35.7600/kVA
Demand charge
>300km<=600km
<500V
Not specified
258.6100/kVA
36.1100/kVA
Demand charge
>600km<=900km
<500V
Not specified
261.2300/kVA
36.4900/kVA
Demand charge
>900km
<500V
Not specified
263.8000/kVA
36.8500/kVA
Demand charge
<=300km
>=500V<66kV
Not specified
247.7400/kVA
34.6400/kVA
Demand charge
>300km<=600km
>=500V<66kV
Not specified
250.2300/kVA
34.9400/kVA
Demand charge
>600km<=900km
>=500V<66kV
Not specified
252.7800/kVA
35.3200/kVA
Demand charge
>900km
>=500V<66kV
Not specified
255.3000/kVA
35.6400/kVA
Demand charge
<=300km
>=66kV<132kV
Not specified
238.7200/kVA
33.3600/kVA
Demand charge
>300km<=600km
>=66kV<132kV
Not specified
241.0900/kVA
33.6900/kVA
Demand charge
>600km<=900km
>=66kV<132kV
Not specified
243.5200/kVA
34.0100/kVA
Demand charge
>900km
>=66kV<132kV
Not specified
245.9800/kVA
34.3800/kVA
Demand charge
<=300km
>132kV
Not specified
230.2800/kVA
32.1700/kVA
Demand charge
>300km<=600km
>132kV
Not specified
232.6200/kVA
32.4900/kVA
Demand charge
>600km<=900km
>132kV
Not specified
234.9700/kVA
32.8300/kVA
Demand charge
>900km
>132kV
Not specified
237.3300/kVA
33.1300/kVA
Electrification and rural subsidy
Not specified
Not specified
Not specified
0.0858/kWh
Excess NAC charge
<=300km
<500V
Not specified
9.6700/kVA
Excess NAC charge
>300km<=600km
<500V
Not specified
9.7100/kVA
Excess NAC charge
>600km<=900km
<500V
Not specified
9.8400/kVA
Excess NAC charge
>900km
<500V
Not specified
9.8900/kVA
Excess NAC charge
<=300km
>=500V<66kV
Not specified
8.8200/kVA
Excess NAC charge
>300km<=600km
>=500V<66kV
Not specified
8.9200/kVA
Excess NAC charge
>600km<=900km
>=500V<66kV
Not specified
8.9800/kVA
Excess NAC charge
>900km
>=500V<66kV
Not specified
9.0800/kVA
Excess NAC charge
<=300km
>=66kV<132kV
Not specified
8.5900/kVA
Excess NAC charge
>300km<=600km
>=66kV<132kV
Not specified
8.6500/kVA
Excess NAC charge
>600km<=900km
>=66kV<132kV
Not specified
8.7200/kVA
Excess NAC charge
>900km
>=66kV<132kV
Not specified
8.7900/kVA
Excess NAC charge
<=300km
>132kV
Not specified
10.8700/kVA
Excess NAC charge
>300km<=600km
>132kV
Not specified
10.9700/kVA
Excess NAC charge
>600km<=900km
>132kV
Not specified
11.1200/kVA
Excess NAC charge
>900km
>132kV
Not specified
11.2000/kVA
Network access charge
<=300km
<500V
Not specified
19.2900/kVA
Network access charge
>300km<=600km
<500V
Not specified
19.2900/kVA
Network access charge
>600km<=900km
<500V
Not specified
19.2900/kVA
Network access charge
>900km
<500V
Not specified
19.2900/kVA
Network access charge
<=300km
>=500V<66kV
Not specified
17.6800/kVA
Network access charge
>300km<=600km
>=500V<66kV
Not specified
17.6800/kVA
Network access charge
>600km<=900km
>=500V<66kV
Not specified
17.6800/kVA
Network access charge
>900km
>=500V<66kV
Not specified
17.6800/kVA
Network access charge
<=300km
>=66kV<132kV
Not specified
6.3200/kVA
Network access charge
>300km<=600km
>=66kV<132kV
Not specified
6.3200/kVA
Network access charge
>600km<=900km
>=66kV<132kV
Not specified
6.3200/kVA
Network access charge
>900km
>=66kV<132kV
Not specified
6.3200/kVA
Transmission network charge
<=300km
<500V
Not specified
9.6700/kVA
Transmission network charge
>300km<=600km
<500V
Not specified
9.7100/kVA
Transmission network charge
>600km<=900km
<500V
Not specified
9.8400/kVA
Transmission network charge
>900km
<500V
Not specified
9.8900/kVA
Transmission network charge
<=300km
>=500V<66kV
Not specified
8.8200/kVA
Transmission network charge
>300km<=600km
>=500V<66kV
Not specified
8.9200/kVA
Transmission network charge
>600km<=900km
>=500V<66kV
Not specified
8.9800/kVA
Transmission network charge
>900km
>=500V<66kV
Not specified
9.0800/kVA
Transmission network charge
<=300km
>=66kV<132kV
Not specified
8.5900/kVA
Transmission network charge
>300km<=600km
>=66kV<132kV
Not specified
8.6500/kVA
Transmission network charge
>600km<=900km
>=66kV<132kV
Not specified
8.7200/kVA
Transmission network charge
>900km
>=66kV<132kV
Not specified
8.7900/kVA
Transmission network charge
<=300km
>132kV
Not specified
10.8700/kVA
Transmission network charge
>300km<=600km
>132kV
Not specified
10.9700/kVA
Transmission network charge
>600km<=900km
>132kV
Not specified
11.1200/kVA
Transmission network charge
>900km
>132kV
Not specified
11.2000/kVA
Urban low voltage subsidy charge
Not specified
>=66kV<132kV
Not specified
15.4800/kVA
Urban low voltage subsidy charge
Not specified
>132kV
Not specified
15.4800/kVA