A large Free State broiler house was operating perilously close to its Eskom supply limit, with frequent breaker trips threatening business continuity. With no more capacity available from Eskom, Augos installed a Power Factor Correction system sized to the site's load, cutting maximum demand and freeing headroom within the existing limit. The trips stopped, operations stabilised, and equipment stress fell.
In the heart of the Free State, a prominent broiler house faced a critical challenge: insufficient electrical capacity from Eskom. The facility was operating perilously close to its maximum supply, and frequent breaker trips disrupted operations and threatened business continuity for the entire agri-processing site.
The client had explored various options to secure additional Eskom capacity without success, a common bottleneck for industrial users in the region. The constant tripping caused disruptive downtime and risked damage to vital, temperature-sensitive equipment.
Recognising the urgent need, Augos proposed a targeted Power Factor Correction system. PFC improves the power factor of an electrical system, which enhances efficiency and, critically, optimises the use of available capacity without expensive infrastructure changes.
Augos assessed the broiler house's unique operational load and implemented a tailored PFC system to address the specific challenge of capacity limitation.
The installation delivered rapid, tangible benefits:
The site was operating perilously close to its Eskom supply limit, with frequent breaker trips that disrupted operations and threatened business continuity for the whole agri-processing facility.
They had explored options to secure additional Eskom capacity without success, a common bottleneck for industrial users in the region. A different approach was needed.
PFC improves the site's power factor, which reduces the maximum demand (kVA) drawn for the same real work. That instantly frees headroom within the existing supply, with no expensive infrastructure upgrade.
The breaker trips stopped, operations stabilised, maximum demand fell, and reduced electrical stress extended equipment life and lowered the risk of failures.
Yes. Any commercial or industrial site running close to its supply limit can often free usable capacity through correctly sized power factor correction, rather than a costly utility upgrade.
Book a demo with one of our energy experts.