Case study · Milling
Cutting a closing mill's NMD from 1,500 kVA to 175 kVA.
As Pioneer Foods' Estcourt Mill closed, Augos asked the Inkosi Langalibalele Local Municipality to reduce its notified maximum demand from 1,500 kVA to 175 kVA. The municipality applied it from 1 July 2025, and the first bill at the new NMD shows it. At the 2025/26 demand rate of R332.91 per kVA, Augos calculates the saving at R441,105.75 a month.
- A closing plant keeps paying for its notified maximum demand until someone asks the utility to reduce it.
- Augos requested a reduction from 1,500 kVA to 175 kVA on the client's behalf before the plant shut at the end of May 2025.
- The municipality noted the reduction by email on 23 May 2025, effective 1 July 2025.
- The first bill at the new NMD charged 175 kVA at R332.91 per kVA. On that rate the saving is R441,105.75 a month, all of it in the demand charge.
As Pioneer Foods' Estcourt Mill shut down, Augos asked the Inkosi Langalibalele Local Municipality to reduce the site's notified maximum demand (NMD) from 1,500 kVA to 175 kVA. The municipality noted the reduction by email on 23 May 2025, effective 1 July 2025, and the first bill at the new NMD charged 175 kVA. At the 2025/26 demand rate of R332.91 per kVA, Augos calculates the saving at R441,105.75 a month, all of it in the demand charge.
What was the situation?
The mill, in Estcourt, KwaZulu-Natal, is part of Pioneer Foods, now PepsiCo South Africa. It was closing, with the plant shutting at the end of May 2025.
The site was on the municipality's Scale 7 tariff, an industrial time-of-use tariff, with a notified maximum demand of 1,500 kVA. The demand rate on its bills was R170.96 per kVA in 2024/25, rising to R332.91 per kVA from July 2025. That NMD was sized for a working mill. Once production stopped, the site would still be billed on capacity it no longer needed, unless someone asked the municipality to change it.
What did Augos do?
Augos requested the reduction on the client's behalf, as its appointed representative, before the plant closed. The NMD was reduced to 175 kVA.
There was one complication. An earlier letter from another party had asked for 100 kVA. The municipality took Augos's letter as the most recent request and worked from that.
Augos also prepared a savings schedule for PepsiCo, setting out the effect of the new NMD on the site's charges.
What did the municipality confirm?
In its email of 23 May 2025, the municipality confirmed receipt of the request and noted the reduction. It said its new tariffs take effect from 1 July, so the change would be effective from 01 July 2025.
The bill confirms it. The municipality's invoice of 31 July 2025, the first at the new NMD, charges the demand on a minimum of 175 kVA at R332.91 per kVA: R58,259.25. The site's actual demand that month read 120 kVA, so the bill is set by the new minimum, not the old 1,500 kVA.
The result and how it was calculated
The saving is an Augos calculation on the demand rate of the July 2025 bill, R332.91 per kVA:
- Demand charge at an NMD of 1,500 kVA: R499,365.00
- Demand charge at an NMD of 175 kVA: R58,259.25, as billed
- Monthly saving: R441,105.75
All figures are ex VAT. The whole difference is the demand charge: 1,325 kVA fewer, at R332.91 per kVA. Energy charges do not change, because the reduction changes only the capacity billed.
The rate matters as much as the reduction. The municipality's demand rate almost doubled in the 2025/26 tariff year, from R170.96 to R332.91 per kVA. At the 2024/25 rate, the same 1,325 kVA was worth R226,522.00 a month; at the rate the site is billed on today, it is worth R441,105.75.
Why does NMD matter so much?
Because demand-based tariffs bill capacity as well as energy. Where the demand charge is set by the notified maximum demand, or held up by a minimum based on it, an oversized NMD keeps billing for capacity the site does not use. For a site that is closing, downsizing or running a much smaller load, the NMD is often the largest single item that can be changed with one letter.
The same thinking applied at another Pioneer Foods site, Continental Beverages in Bloemfontein, where production stopped and the site moved to a tariff with no demand or network access charge.
What to check on your own site
- What is the site's notified maximum demand, and when was it last reviewed?
- How does the NMD compare with the highest demand the site has actually measured over the last 12 months?
- Is a plant closure, downsizing or shift change coming up? Apply before it happens, not after.
- When does the utility apply changes? Some apply them from the start of the new tariff year.
- Has anyone else written to the utility about the same account? Make sure the request on file is the one you want.
- Once the change is in place, check the first bill at the new NMD line by line, and check the demand rate each new tariff year: a cut made before a rate increase is worth more after it.
Tariff analysis and bill verification are core to what Augos does. See how tariff optimisation works, or read how electricity tariffs work. To review your own sites, book a demo or call 087 093 6174.
In this story
The tools behind the result.
Tariff optimisation
Your measured usage priced against every tariff, with the supply and NMD checked too.
Explore ›Continental Beverages, Bloemfontein
Another Pioneer Foods site, moved to a tariff without demand charges after production stopped.
Explore ›Pioneer Foods tariff programme
Seven tariffs changed across Pioneer Foods sites by early 2021.
Explore ›Bill verification
Every bill checked against the tariff and the measured data.
Explore ›The rest of Augos Energy
Energy management
Each site metered, priced on its own tariff and every bill checked against the meter.
Explore ›Power factor correction
Power factor and demand measured at the half-hour that sets the bill.
Explore ›Tenant billing
Each tenant sub-metered and billed on what they used.
Explore ›Energy procurement support
Wheeling, PPA and solar offers replayed on your own 30-minute load.
Explore ›Energy reporting
Measured data by site and period, as downloads, by API or as AI-ready exports.
Explore ›More case studies
More results, with their basis.
Questions
What happens to the demand charge when a factory closes?
It keeps billing on the notified maximum demand until the customer asks the utility to reduce it. At Pioneer Foods' Estcourt Mill, the NMD stood at 1,500 kVA while the plant was shutting down.
How do you reduce notified maximum demand with a municipality?
The customer, or a representative it appoints, writes to the municipality asking for the new NMD. For the Estcourt Mill, Augos sent the request and the Inkosi Langalibalele Local Municipality noted the reduction to 175 kVA, effective 1 July 2025.
How much can reducing NMD save?
It depends on the demand rate and how far the NMD falls. At the Estcourt Mill, cutting 1,325 kVA at the 2025/26 demand rate of R332.91 per kVA reduces the bill by R441,105.75 a month, an Augos calculation. At the 2024/25 rate of R170.96 the same cut was worth R226,522.00 a month.
When does an NMD reduction take effect?
When the utility applies it, which may be at the start of a new tariff year. The Inkosi Langalibalele Local Municipality made the Estcourt change effective 1 July 2025, when its new tariffs took effect.
Who can apply for an NMD reduction?
The account holder, or a representative it appoints in writing. Augos manages tariff and NMD applications with the utility on the client's behalf, as the client's appointed representative.
Free site assessment
Assess your measurement point and get a quote.
Tell us the site type, supply size and number of sites, photograph the measurement point, and we quote. Electricity now; water, gas and fuel next.